Rural Area Twinning - Phases 2 and 3

Osoyoos, British Columbia

completeDrinking WaterGIS
Federal contribution
$2.3M
$2,308,000
Federal share40%

of $5.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 27, 2019
202020212022
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Osoyoos
Construction start
Jul 6, 2020(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 1, 2020
  • Construction end6 weeks earlyforecast Dec 15, 2022

Also in Osoyoos

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54121 in the federal list. How to read these figures.