2017 Sanitary Sewer Infrastructure Rehabilitation Program

Osoyoos, British Columbia

completeWastewaterCWWF
Federal contribution
$510,000
Federal share50%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Osoyoos
Construction start
Jun 17, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 1, 2017
  • Construction end4 weeks earlyforecast Dec 31, 2018

Also in Osoyoos

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49813 in the federal list. How to read these figures.