New Shelter for the Alliston District Humane Society

Adjala-Tosorontio, Ontario

completeOtherISF
Federal contribution
$266,667
Federal share33%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
Apr 19, 2010(actual)
Construction end
Aug 8, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Oct 1, 2009
  • Construction end5 weeks earlyforecast Sep 15, 2010