Accessibility Upgrades to 3 Municipal Public Parks

Adjala-Tosorontio, Ontario

completeRecreationCCRIS
Federal contribution
$106,387
Federal share40%

of $266.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 8, 2021
202120222023
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Jul 11, 2022(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 15, 2022