Reconstruction of a Section of Concession Road 5 Including Replacement of Two Bridge Structures

Adjala-Tosorontio, Ontario

completeHighways and RoadsRNIS
Federal contribution
$1.2M
$1,173,000
Federal share50%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 19, 2020
202120222023
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jul 20, 2020(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction end9 months lateforecast Sep 30, 2022

Also in Adjala-Tosorontio

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54564 in the federal list. How to read these figures.