Renovation of the Bruyère Centre for Immigrants
Federal contribution
$375,000
Federal share50%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 1, 2010
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Catholic Immigration Centre of Ottawa
- Construction start
- Feb 1, 2010(actual)
- Construction end
- Mar 23, 2011(actual)
Against the original forecast
- Construction start5 weeks earlyforecast Mar 9, 2010