Water Metering and Leak Detection

Pemberton, British Columbia

completeDrinking WaterISF
Federal contribution
$166,667
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Pemberton
Construction start
Jun 7, 2010(actual)
Construction end
Mar 4, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Apr 30, 2010
  • Construction end4 weeks earlyforecast Mar 31, 2011

Also in Pemberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35646 in the federal list. How to read these figures.