Back to projects

Repairs to Highway 161 in Nantes

Nantes, Quebec

completeHighways and RoadsISF
Federal contribution
$871,748
Federal share50%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 12, 2010(actual)
Construction end
Jun 15, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2010
  • Construction end2 weeks earlyforecast Jul 1, 2011

Also in Nantes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35785 in the federal list. How to read these figures.