Repairs to Highway 161 in Nantes
Federal contribution
$871,748
Federal share50%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 1, 2010
- Construction end2 weeks earlyforecast Jul 1, 2011
Also in Nantes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35785 in the federal list. How to read these figures.