Water Systems Upgrades
Federal contribution
$237,050
Federal share40%
of $592.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Nantes
- Construction start
- May 25, 2021(actual)
- Construction end
- Aug 24, 2021(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Sep 30, 2021
Also in Nantes