Renewal of water pipes
Federal contribution
$688,559
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 26, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Nantes
- Construction start
- Aug 7, 2017(actual)
- Construction end
- Nov 21, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 5, 2017
- Construction end2 months earlyforecast Feb 1, 2018
Also in Nantes