Repairs to Highway 117 in Rouyn-Noranda
Federal contribution
$742,722
Federal share44%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- May 25, 2010(actual)
- Construction end
- Jun 17, 2011(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 15, 2010
- Construction end9 months lateforecast Sep 30, 2010
Also in Rouyn-Noranda
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35790 in the federal list. How to read these figures.