Johnson Street Bridge

Victoria, British Columbia

completeHighways and RoadsMIC
Federal contribution
$21.0M
$21,000,000
Federal share24%

of $86.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 24, 2009
20102012201420162018
Built

Approved 6 weeks after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
The City of Victoria
Construction start
May 17, 2013(actual)
Construction end
Jul 8, 2018(actual)

Against the original forecast

  • Construction start20 months lateforecast Oct 1, 2011
  • Construction end15 months earlyforecast Sep 30, 2019

Also in Victoria

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35805 in the federal list. How to read these figures.