Johnson Street Bridge
Federal contribution
$21.0M
$21,000,000
Federal share24%
of $86.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 24, 2009
20102012201420162018
Built
Approved 6 weeks after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- The City of Victoria
- Construction start
- May 17, 2013(actual)
- Construction end
- Jul 8, 2018(actual)
Against the original forecast
- Construction start20 months lateforecast Oct 1, 2011
- Construction end15 months earlyforecast Sep 30, 2019
Also in Victoria