Northwest Transmission Line
Federal contribution
$130.0M
$130,000,000
Federal share21%
of $605.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2009
20102011201220132014
Built
Approved 5 weeks after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- Province of British Columbia
- Construction start
- Oct 10, 2011(actual)
- Construction end
- Jul 15, 2014(actual)
Against the original forecast
- Construction start7 months lateforecast Mar 24, 2011
- Construction end3 months earlyforecast Sep 30, 2014
Also in Victoria
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39246 in the federal list. How to read these figures.