Northwest Transmission Line

Victoria, British Columbia

completeGreen EnergyGIF
Federal contribution
$130.0M
$130,000,000
Federal share21%

of $605.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2009
20102011201220132014
Built

Approved 5 weeks after the announcement.

Program
Green Infrastructure Fund
Construction start
Oct 10, 2011(actual)
Construction end
Jul 15, 2014(actual)

Against the original forecast

  • Construction start7 months lateforecast Mar 24, 2011
  • Construction end3 months earlyforecast Sep 30, 2014