Conveyance System Project for the Capital Regional District (Victoria)

Victoria, British Columbia

completeWastewaterGIF
Federal contribution
$50.0M
$50,000,000
Federal share34%

of $148.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2012
20132015201720192021
Built
Program
Green Infrastructure Fund
Construction start
Jul 2, 2013(actual)
Construction end
May 3, 2021(actual)

Against the original forecast

  • Construction start11 months lateforecast Aug 1, 2012
  • Construction end5 weeks lateforecast Mar 31, 2021