Highway 101 Repaving
Federal contribution
$1.1M
$1,130,086
Federal share32%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
Approved 3 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Apr 6, 2010(actual)
- Construction end
- Jul 1, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2010
- Construction end4 months earlyforecast Oct 31, 2010
Also in Victoria