Highway 101 Repaving

Victoria, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,130,086
Federal share32%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
2010
Built

Approved 3 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Apr 6, 2010(actual)
Construction end
Jul 1, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 1, 2010
  • Construction end4 months earlyforecast Oct 31, 2010