Little Narrows Ferry Replacement
Federal contribution
$3.0M
$3,026,423
Federal share50%
of $6.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2019
201920202021202220232024
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Province of Nova Scotia
- Construction start
- Jul 2, 2020(actual)
- Construction end
- Dec 29, 2023(actual)
Against the original forecast
- Construction end21 months lateforecast Mar 31, 2022