Back to projects

Cabot Trail Rehabilitation - Trunk 30

Victoria, Nova Scotia

completeHighways and RoadsRNIS
Federal contribution
$4.3M
$4,300,000
Federal share50%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 30, 2020
2021
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Province of Nova Scotia
Construction start
Aug 3, 2020(actual)
Construction end
Oct 25, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2020
  • Construction end8 months earlyforecast Jun 30, 2022

Also in Victoria