Assiniboine Bikeway

Winnipeg, Manitoba

completeHighways and RoadsISF
Federal contribution
$41,666
Federal share33%

of $125.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 30, 2010(actual)
Construction end
Aug 19, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2010
  • Construction end2 weeks lateforecast Aug 5, 2011