Watermain Replacement

Saint-Malachie, Quebec

completeWastewaterISF
Federal contribution
$1.0M
$1,005,756
Federal share33%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 30, 2010(actual)
Construction end
Feb 7, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2010
  • Construction end5 months earlyforecast Jun 24, 2011

Also in Saint-Malachie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35919 in the federal list. How to read these figures.