completeWastewaterISF
Federal contribution
$556,710
Federal share23%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 30, 2010(actual)
Construction end
Oct 15, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2010