Renewal of water pipes

Saint-Malachie, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.5M
$1,469,879
Federal share38%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20172018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 10, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Saint-Malachie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48861 in the federal list. How to read these figures.