Silver Ave Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$651,514
Federal share32%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 3, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 15, 2010