Moray Street Pathway
Federal contribution
$94,899
Federal share24%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 3, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 30, 2010
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36564 in the federal list. How to read these figures.