Transcona Trail Phase 2
Federal contribution
$342,138
Federal share26%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Dec 20, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2010
- Construction end10 months earlyforecast Oct 17, 2011