Dugald Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$230,303
Federal share26%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011201220132014
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Sep 1, 2010(actual)
Construction end
Nov 14, 2013(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2010
  • Construction end4 weeks lateforecast Oct 15, 2013