Wilkes Avenue Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$63,482
Federal share21%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
May 13, 2010(actual)
Construction end
Jul 29, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 15, 2010