Eugenie/Des Meurons Bikeway
Federal contribution
$41,666
Federal share33%
of $125.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Nov 10, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2010
- Construction end9 months earlyforecast Aug 12, 2011
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36579 in the federal list. How to read these figures.