Archibald Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$260,715
Federal share29%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Jul 26, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction end2 months lateforecast Aug 26, 2011

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36580 in the federal list. How to read these figures.