Bison Drive Pathway
Federal contribution
$80,000
Federal share33%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 8, 2010(actual)
- Construction end
- Nov 10, 2010(actual)
Against the original forecast
- Construction end10 months earlyforecast Aug 31, 2011
Also in Winnipeg