Bison Drive Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$80,000
Federal share33%

of $240.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Sep 8, 2010(actual)
Construction end
Nov 10, 2010(actual)

Against the original forecast

  • Construction end10 months earlyforecast Aug 31, 2011

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36582 in the federal list. How to read these figures.