Dakota/Dunkirk Pathway Phase 1
Federal contribution
$444,280
Federal share32%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 29, 2010(actual)
- Construction end
- Oct 5, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jul 15, 2010
- Construction end13 months earlyforecast Oct 31, 2011