Kildonan Golf Course Pathway
Federal contribution
$166,666
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 20, 2010(actual)
- Construction end
- Aug 18, 2011(actual)
Against the original forecast
- Construction end7 weeks lateforecast Jun 30, 2011
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36585 in the federal list. How to read these figures.