Hay Street Bikeway
Federal contribution
$72,799
Federal share32%
of $225.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Oct 4, 2010(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Nov 30, 2010