Nassau Bikeway

Winnipeg, Manitoba

completeHighways and RoadsISF
Federal contribution
$75,000
Federal share33%

of $225.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Sep 20, 2010(actual)
Construction end
Jul 15, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 15, 2010
  • Construction end4 weeks earlyforecast Aug 12, 2011