York Avenue Bike Lanes
Federal contribution
$12,318
Federal share21%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 1, 2010(actual)
- Construction end
- Oct 1, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2010
- Construction end4 weeks earlyforecast Oct 31, 2010
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36590 in the federal list. How to read these figures.