St. Mary Avenue Bike Lane
Federal contribution
$12,088
Federal share20%
of $60.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Oct 1, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 30, 2010
- Construction end4 weeks earlyforecast Oct 31, 2010