Dakota/Dunkirk Pathway Phase 2

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$300,000
Federal share33%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 23, 2010(actual)
Construction end
Nov 10, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2010
  • Construction end11 months earlyforecast Oct 15, 2011