Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Oct 11, 2011(actual)
- Construction end
- Oct 31, 2011(actual)