Kildare Avenue Bikeway
Federal contribution
$151,116
Federal share22%
of $675.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 30, 2010(actual)
- Construction end
- Oct 15, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2010
- Construction end7 weeks earlyforecast Nov 30, 2010