Bannatyne/McDermot Bikeway

Winnipeg, Manitoba

completeHighways and RoadsISF
Federal contribution
$14,080
Federal share6%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 1, 2011(actual)
Construction end
Sep 8, 2011(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Aug 15, 2011
  • Construction end3 weeks earlyforecast Sep 30, 2011

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36598 in the federal list. How to read these figures.