Machray Bikeway
Federal contribution
$175,112
Federal share19%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Oct 18, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2010
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36604 in the federal list. How to read these figures.