Pritchard Bikeway
Federal contribution
$119,380
Federal share13%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Aug 23, 2010(actual)
- Construction end
- Oct 19, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 1, 2010
- Construction end6 weeks earlyforecast Nov 30, 2010
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36605 in the federal list. How to read these figures.