Pritchard Bikeway

Winnipeg, Manitoba

completeHighways and RoadsISF
Federal contribution
$119,380
Federal share13%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 11, 2009
ApprovedOct 6, 2009
2010
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 23, 2010(actual)
Construction end
Oct 19, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 1, 2010
  • Construction end6 weeks earlyforecast Nov 30, 2010

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36605 in the federal list. How to read these figures.