Sherwin Road Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$121,847
Federal share24%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Jul 26, 2010(actual)
Construction end
Feb 18, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 30, 2010
  • Construction end5 months lateforecast Sep 30, 2010

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36606 in the federal list. How to read these figures.