Sherwin Road Pathway
Federal contribution
$121,847
Federal share24%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2009
20102011
Built
Approved 4 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Feb 18, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 30, 2010
- Construction end5 months lateforecast Sep 30, 2010