Seine River Pathway

Winnipeg, Manitoba

completeActive TransportationISF
Federal contribution
$83,333
Federal share33%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
20102011
Built

Approved 4 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Winnipeg
Construction start
Aug 15, 2011(actual)
Construction end
Oct 3, 2011(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Oct 21, 2011