Schedule

AnnouncedSep 16, 2009
ApprovedOct 26, 2009
2010
Built

Approved 6 weeks after the announcement.

Program
G8 Legacy Fund
Construction start
Oct 26, 2009(actual)
Construction end
Jun 25, 2010(actual)