Golden Pheasant Wastewater Treatment Plant - Upgrade, Optimization and rehabilitation of Preliminary and Secondary Treatment processes

Muskoka, Ontario

completeWastewaterCWWF
Federal contribution
$3.1M
$3,104,826
Federal share48%

of $6.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2017201920212023
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 24, 2016(actual)
Construction end
Dec 23, 2022(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jan 2, 2017