Bracebridge Water Distribution System Rehabilitation

Muskoka, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.0M
$1,999,200
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
202320242025202620272028
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
May 6, 2024(actual)
Construction end
Nov 30, 2027(forecast)