Boulevard Pump Station
Federal contribution
$378,036
Federal share27%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Squamish
- Construction start
- Dec 24, 2009(actual)
- Construction end
- Nov 10, 2010(actual)
Against the original forecast
- Construction start8 weeks lateforecast Nov 1, 2009
- Construction end7 weeks earlyforecast Dec 31, 2010
Also in Squamish
- Brennan Park Recreation Centre Retrofit and Upgrade$11.8M
- Squamish - Brennan Park Recreation Centre Building Envelope Upgrade$5.7M
- Squamish - Mamquam Wastewater Treatment Plant Upgrade$4.0M
- Squamish - Xwu'nekw Park Sea Dike at Mamquam Blind Channel$2.2M
- Squamish River Dike Raising - Upper Jimmy Jimmy (Judd) Slough$2.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36779 in the federal list. How to read these figures.