Watermain Looping

Pemberton, British Columbia

completeDrinking WaterISF
Federal contribution
$160,164
Federal share25%

of $643.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Pemberton
Construction start
May 10, 2010(actual)
Construction end
Nov 12, 2010(actual)

Against the original forecast

  • Construction end3 months lateforecast Aug 6, 2010

Also in Pemberton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36790 in the federal list. How to read these figures.