92nd Avenue Storm Water Drainage Upgrades
Dawson Creek, British Columbia
Federal contribution
$257,333
Federal share33%
of $772.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Dawson Creek
- Construction start
- Oct 30, 2009(actual)
- Construction end
- Jun 24, 2010(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2010
- Construction end2 months earlyforecast Aug 27, 2010
Also in Dawson Creek
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36863 in the federal list. How to read these figures.