City of Dawson Creek - Zone 1 Potable Water Reservoir

Dawson Creek, British Columbia

completeDrinking WaterSCF
Federal contribution
$1.7M
$1,666,666
Federal share33%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2015
2016201820202022
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Dawson Creek
Construction start
Jun 1, 2016(actual)
Construction end
Jun 12, 2022(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 13, 2016
  • Construction end3 months earlyforecast Sep 2, 2022

Also in Dawson Creek

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46092 in the federal list. How to read these figures.