City of Dawson Creek - Zone 1 Potable Water Reservoir
Dawson Creek, British Columbia
Federal contribution
$1.7M
$1,666,666
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2015
2016201820202022
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Dawson Creek
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Jun 12, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 13, 2016
- Construction end3 months earlyforecast Sep 2, 2022
Also in Dawson Creek
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46092 in the federal list. How to read these figures.